PHPA Channel Marker Replacement

Project Details

  • Client Pilbara Ports Authority
  • EPCM No
  • Location Port Hedland Shipping Channel
  • Duration 3 months

In March 2012 TAMS were awarded a fixed price lump sum contract by the Port Hedland Port Authority for replacement of channel beacons 24, 34 and 36. Due to the congested nature of the PHPA cargo berths, the 1200 OD piles, top sections and ladders were fabricated in Perth and barged to site thereby removing the need to access the port facilities.  The piles were installed using our piling barge ‘ASL 96’ equipped with a 200t crane and 16t Junttan piling hammer. 